Energy Brief — Saturday, 21 November 2026

Solar efficiency records fall, storage patents tip a historic inflection point, and two continents advance grid-scale storage.

01 / The Day

SATURDAY 21 NOV 2026, ranked

07

JinkoSolar sets 35.24% perovskite-TOPCon tandem record

JinkoSolar has achieved a 35.24% conversion efficiency on a perovskite-TOPCon tandem solar cell, setting a new world record verified by an independent laboratory.

  • Previous record: 34.6% (LONGi, July 2026)
  • Cell size: 1 cm2 — lab scale, not production module
  • Perovskite top cell stability achieved at 1,000-hour damp heat
Why it mattersPerovskite-silicon tandem efficiency gains are compressing; the race to production-scale is now the bottleneck.

Solid-state battery patents surpass lithium-ion for first time

Annual patent filings for solid-state battery technology have exceeded conventional lithium-ion filings for the first time in history, with Toyota and Samsung leading the new cohort.

  • Solid-state filings: 14,200 (2025) vs Li-ion: 13,800
  • Toyota holds 2,700 patents — most of any single filer
  • WIPO tracking shows acceleration in oxide electrolyte designs
Why it mattersPatent intensity is the leading indicator of commercial readiness; solid-state is now past the research inflection.

China grid-connects world first artificial-cavern CAES plant

China has connected the world first compressed-air energy storage plant built inside an artificially excavated underground cavern to its national grid, achieving 300 MW and 1,500 MWh.

  • 300 MW / 1,500 MWh; round-trip efficiency: 71.4%
  • Cavern blasted in Hubei province bedrock; no salt dome required
  • Opens CAES deployment to geographies without natural salt formations
Why it mattersArtificial-cavern CAES removes the geological constraint that has limited the technology to a handful of global sites.

Germany: 4GWh BESS projects advance to FID before year-end

German energy storage operators are rushing to reach final investment decisions on 4 GWh of large-scale battery projects before the December 31 deadline for feed-in premium eligibility.

  • Three projects totaling 4 GWh across NRW and Brandenburg
  • FID required by Dec 31 to lock 2026 capacity premium rates
  • Combined capex ~1.4B euros; debt financing secured from KfW
Why it mattersGermany storage pipeline is being pulled forward by subsidy cliffs, compressing construction timelines.

EDF acquires 250MW/1GWh Australian BESS project

EDF Renewables has acquired the Holloway Battery project in New South Wales — a 250 MW and 1 GWh grid-scale storage facility — ahead of a 2027 construction start.

  • Site secured near existing EDF wind assets in NSW
  • Project will export into NEM under long-term capacity contract
  • Part of EDF 3B dollar APAC storage expansion announced in June
Why it mattersEuropean energy majors are accelerating asset acquisitions in Australia as its storage market matures.

Spain requires data centers to run on 80% renewable electricity

Spain new data center regulation requires all facilities above 1 MW to source at least 80% of electricity from certified renewable sources by 2028, with 100% required by 2030.

  • PPAs or on-site generation qualify; REGOs accepted
  • Applies to new builds immediately; existing facilities get 24-month runway
  • Largest EU market to mandate renewable quotas for data centers
Why it mattersAI compute demand and renewable mandates are on a collision course in Spain as hyperscalers expand Iberian capacity.

BAAJA permitting reform passes US Senate; storage industry reacts

The Build America Advanced Jobs Act, which reforms federal permitting for clean energy and storage projects, has passed the US Senate with bipartisan support.

  • BESS projects under 500 MW qualify for expedited 12-month review
  • Eliminates duplicate state-federal permitting for interstate projects
  • NEMA and Energy Storage Association call it decade-defining legislation
Why it mattersPermitting reform has been the single largest bottleneck for US storage deployment; BAAJA removes the legal ceiling.