Germany's 3.2GWh of 4-hour batteries reach construction milestone
A cluster of German battery storage projects totalling 3.2GWh reached construction or final investment decision in mid-October, driven by a January 2027 deadline for a 20-year grid-fee exemption. Projects involve Enertrag, Enlight, Vattenfall, Fluence, and Giga Storage at separate sites.
- Enertrag/Enlight 200MW/840MWh in Brandenburg broke ground October 13; online H1 2028
- Vattenfall/Fluence 254MW/1GWh FID at Brunsbüttel former nuclear site; build starts 2027
- FID before 1 January 2027 required to qualify for 20-year grid-fee exemption in Germany